Status Update

–  RM 967 to Jerry’s Lane will have construction activity related to onsite cut to fill, prep subgrade, and installation of inlets and driveway pipes.
–  These activities will cause minimal impact to traffic.
–  Jerry’s Lane to McKinnon Loop will have construction activity related to onsite cut to fill and installation of driveway pipes.
– This will cause minimal impact to traffic.
–  McKinnon Loop to the Travis County Line will have no construction activity at this time
– These activities will have minimal impacts to traffic.
– Travis County Line to Brodie Lane construction activity includes installation of pipes at Bliss Spillar, sub-grade prep, detours 225 and 248, and traffic switch
– The detour activity will have moderate impacts on traffic.
–  No driveways will be impacted.

*THE TRAFFIC SWITCH AT BLISS SPILLAR WILL OCURR ON 02/07/2014 PENDING WEATHER*