Status Update

Activities for 03/24/2014 to 04/05/2014

  • RM 967 to Jerry’s Lane will have construction activity related to prepping subgrade, base coarse, install curb and gutter, grade ditch, and topsoil
  • These activities will cause minimal impact to traffic
  • Jerry’s Lane to McKinnon Loop will have construction activity related to onsite cut to fill and prep subgrade
  • This will cause minimal impact to traffic
  • McKinnon Loop to the Travis County Line will have construction activity stockpiling materials in the yard
  • These activities will have minimal impacts to traffic
  • Travis County Line to Brodie Lane will have no construction activity at this time
  • No driveways will be impacted