Status Update

Activities for 09/29/2014 to 10/11/2014

  • RM 967 to Jerry’s Lane will have no construction activity at this time.
  • Jerry’s Lane to McKinnon Loop will have construction activity related to culvert B work, culvert B wing walls, and excavation and embankment work.
  • McKinnon Loop to the Travis County Line will have construction activity related to excavation embankment, install 24” RCP, and culvert E wing wall work.
  • Travis County Line to Brodie Lane will have construction activity related to the installation of 24” RCP, prepping subgrade, base coarse, and topsoil.

These activities will have minimal impact to the traveling public.